Pool Redevelopment

  • Date: 01 November 2015
  • Category: News
Pool Update Jan 2016

Update: 

Monday 1st February - The pool is now open for public use!


Announcement

Pool will reopen to patrons on Monday 1st February 2016!

We will be celebrating Carlton Baths 100th Birthday and our new pool with an Open Day party on Saturday 13th February

Exciting news, we hope to see everyone there to celebrate!

December 2015

Exciting News!

Our pool is in the final stages of redevelopment. 

Updates on exact open dates will be shared as soon as possible.

At this stage, we can estimate that the pool will re open very early in February 2016!

Stay tuned for official dates.. 

 

July 14th 2015


Carlton Baths Redevelopment - Stage Two update for the website

Stage Two of the Carlton Baths redevelopment started 7 April 2015 and is focusing on:

  • the external landscape
  • a new and relocated toddler’s pool with a range of new and modern play equipment
  • modifications to the main pool including a ramp and re-levelled floor to provide a higher level of access to the community
  • a range of other landscape features including shade sails and further tree planting
  • modernised and relocated plant room.

This exciting project will improve the amenity of the existing outdoor space at the facility and City of Melbourne’s ongoing commitment to improving community infrastructure.

 

 

 

 

As works were being undertaken we discovered a range of structural issues within the existing pool. This means that we need to replace the entire pool shell. As a result, Carlton Baths stage two refurbishment is now expected to be complete early in the New Year.

Local residents may experience some minor disruptions during the redevelopment. We will work with the builder to minimise any disruption during the redevelopment and ensure that those that are directly affected will be you are kept informed.

 

Despite some set backs work is well underway. Take a look at the progress of redevelopment up until now.

CBPoolMay2015 SM CBPoolJune2015 SM

We will continue to provide progress pictures as we go. We hope you enjoy seeing how the new outdoor aquatic facility develops as we do. 

Check out the link below to give you an animated interpretation of what this new and exciting space will look like.  Plans for this stage of the redevelopment are on display at Carlton Baths reception.

 

Animated interpretation of Carlton Baths Stage Two works

 

 

For more information relating to these works, please contact Osei Owusu-Afriyie Senior Project Manager on 9658 8625 or email carlton-baths-redev@melbourne.vic.gov.au



April 1st 2015

 

Exciting News – Carlton Baths Stage 2 Redevelopment Approved

Check out the link!

http://bit.ly/CarltonPoolRedev_2015

 On the 31st of March 2015 the City of Melbourne Councillors met and approved the documentation & design for Carlton Baths Stage 2 Redevelopment.

 

 During the redevelopment our primary focus is minimising the impact to Centre operations. Works are due to commence immediately to ensure construction is completed by summer 2015.  The planned construction period is the Tuesday 7th April 2015 till at least January 2016. This means that final public access to the aquatic area will be on Monday  6th of April 2015

  • If you wish to continue swimming during the redevelopment period you can do so at one of the other Active Melbourne facilities through the reciprocal rights program. Please note that all Aquatic memberships will be automatically placed on free suspension during the period of closure.

 

The redevelopment will focus on external landscape, a new and relocated toddlers pool with a range of new and modern play equipment, modifications to the main pool including a ramp and re-levelled floor to provide a higher level of access to the community, a range of other landscape features including shade sails, further tree planting and a new, up to-date and relocated plant room. 

For more information relating to these works, please contact Osei Owusu-Afriyie Senior Project Manager on 9658 8625 or email carlton-baths-redev@melbourne.vic.gov.au.

Keep an eye on Facebook and the Website for exciting updates of the redevelopment during winter.  


February 10th 2015

Carlton Baths Redevelopment - Stage Two

In 2012 City of Melbourne completed Stage One of the redevelopment.

 Carlton Baths redevelopment included:

  • a new entrance/reception area incorporating Family Services functions
  •  new group fitness rooms
  •  a new cycling studio
  • upgraded change facilities
  • a new weights room/gymnasium.

 

 

Subject to budget approval, Council is currently tendering for the construction of Stage Two of the redevelopment. The works for stage two will focus on:

  • the external landscape
  • a new and relocated toddlers pool with a range of new and modern play equipment
  • modifications to the main pool including a ramp and re-levelled floor to provide a higher level of access to the community
  •  a range of other landscape features including shade sails and further tree planting
  • up to-date and relocated plant room.

 

This exciting project will improve the amenity of the existing outdoor space at the facility and is an important element of City of Melbourne’s community infrastructure.

 

Should budget approval be provided, the pool area at Carlton Baths is planned to close in early April 2015 and plan reopen for use in early 2016. This will be confirmed as soon as possible, at the completion of the tender process.

 

Plans for this stage of the redevelopment will be on display at Carlton Baths reception or by visiting www.carltonbaths.ymca.org.au from early February 2015.

 

Local residents and facility users of the outdoor pool and toddlers areas may experience some disruptions during the redevelopment. We will provide further detailed and timely information to all those who will be directly affected as the need arises. We apologise for any inconvenience these works may cause.

 

For more information relating to these works, please contact Osei Owusu-Afriyie Senior Project Manager on 9658 8625 or email carlton-baths-redev@melbourne.vic.gov.au

 